EPRX balancing-capacity market (需給調整市場), day-ahead regime, 2026-10-17 to 2026-11-16: Primary (online) (一次調整力) avg ¥2.97/ΔkW·30min vs cap ¥10, shortfall 8%; Primary offline (一次オフライン) avg ¥2.54/ΔkW·30min vs cap ¥10, shortfall 41%; Secondary ① (二次調整力①) avg ¥3.58/ΔkW·30min vs cap ¥10, shortfall 34%; Secondary ② (二次調整力②) avg ¥2.88/ΔkW·30min vs cap ¥7.21, shortfall 4%. Largest primary-reserve shortfall: Hokuriku 28% of requested ΔkW.
- Primary (online)
- ¥2.97 · 8% short
- Primary offline
- ¥2.54 · 41% short
- Secondary ①
- ¥3.58 · 34% short
- Secondary ②
- ¥2.88 · 4% short
- Tertiary ①
- ¥2.62 · 8% short
- Hokuriku primary shortfall
- 28%
Balancing Market
Area × product · new regime · 2026-03-14 → 2026-11-16 (248 days)
Cell = average cleared ΔkW price (¥/ΔkW·30 min) · max · shortfall rate (red intensity) · cap headroom · awarded / requested MW · hover for detail, click for the day view
| Product | Hokkaido 北海道 | Tohoku 東北 | Tokyo 東京 | Chubu 中部 | Hokuriku 北陸 | Kansai 関西 | Chugoku 中国 | Shikoku 四国 | Kyushu 九州 | All areas |
|---|---|---|---|---|---|---|---|---|---|---|
Primary (online) 一次調整力 cap ¥10 | ||||||||||
| † Primary (online) · Awarded MW can exceed requested MW where composite (複合) awards are counted against this product; the exact EPRX field definition is being confirmed. | ||||||||||
Primary offline 一次オフライン cap ¥10 | ||||||||||
Secondary ① 二次調整力① cap ¥10 | ||||||||||
| † Secondary ① · Awarded MW can exceed requested MW where composite (複合) awards are counted against this product; the exact EPRX field definition is being confirmed. | ||||||||||
Secondary ② 二次調整力② cap ¥7.21 ⚠ composite spillover — hover | ||||||||||
| † Secondary ② · Awarded MW can exceed requested MW where composite (複合) awards are counted against this product; the exact EPRX field definition is being confirmed. | ||||||||||
Tertiary ① 三次調整力① cap ¥7.21 ⚠ composite spillover — hover | ||||||||||
| † Tertiary ① · Awarded MW can exceed requested MW where composite (複合) awards are counted against this product; the exact EPRX field definition is being confirmed. | ||||||||||
Tertiary ② 三次調整力② no cap | ||||||||||
Composite 複合商品 cap ¥10 | ||||||||||
| † Composite · Awarded MW can exceed requested MW where composite (複合) awards are counted against this product; the exact EPRX field definition is being confirmed. | ||||||||||
Weekly balancing card
Mon–Sun area × product heat-map for LinkedIn · shortfall, cleared ΔkW price vs cap and battery share · rule-based headlines, computed live from EPRX results
| price · short % hd to cap · awd/req MW | Hokkaido 北海道 | Tohoku 東北 | Tokyo 東京 | Chubu 中部 | Hokuriku 北陸 | Kansai 関西 | Chugoku 中国 | Shikoku 四国 | Kyushu 九州 | All areas |
|---|---|---|---|---|---|---|---|---|---|---|
Primary (online) 一次調整力 cap ¥10+0.42 w/w | 4.864% 51% hd100/51 | 3.103% 69% hd108/104 | 2.491% 75% hd323/289 | 2.8512% 72% hd215/244 | 4.6454% 54% hd31/67 | 3.8125% 62% hd200/267 | 1.591% 84% hd120/114 | 1.150% 89% hd52/43 | 4.017% 60% hd163/172 | 3.1711% 68% hd146/150 |
Primary offline 一次オフライン cap ¥10+1.36 w/w | 5.8374% 41% hd5/18 | 1.9226% 81% hd47/48 | 0.9929% 90% hd64/89 | 1.9120% 81% hd63/78 | 4.9961% 50% hd13/30 | 7.1540% 28% hd56/91 | 2.5673% 76% hd20/74 | 1.8596% 81% hd0/10 | 1.6419% 84% hd58/62 | 3.3639% 68% hd36/56 |
Secondary ① 二次調整力① cap ¥10+0.36 w/w | 5.0017% 50% hd91/78 | 5.0367% 51% hd56/161 | 2.7129% 73% hd312/433 | 2.251% 78% hd499/218 | 5.8082% 49% hd11/51 | 0.8087% 93% hd30/229 | 1.5815% 84% hd80/27 | 1.3722% 86% hd41/43 | 8.077% 19% hd167/151 | 3.6637% 65% hd143/155 |
Secondary ② 二次調整力② cap ¥7.21+0.02 w/w | 3.895% 46% hd100/65 | 3.882% 46% hd288/258 | 2.380% 67% hd661/85 | 2.250% 69% hd509/222 | 2.693% 62% hd44/40 | 1.738% 76% hd212/208 | 1.590% 78% hd102/51 | 0.902% 87% hd130/62 | 6.132% 15% hd293/198 | 2.843% 61% hd260/132 |
Tertiary ① 三次調整力① cap ¥7.21+0.14 w/w | 3.4731% 52% hd191/273 | 3.922% 46% hd343/311 | 2.5011% 65% hd928/978 | 2.251% 69% hd594/476 | 2.6014% 64% hd98/114 | 1.6715% 77% hd524/612 | 1.759% 76% hd190/196 | 0.982% 86% hd153/145 | 4.757% 34% hd472/465 | 2.6610% 63% hd388/397 |
Tertiary ② 三次調整力② no cap+1.75 w/w | 14.3915% no cap20/23 | 1.430% no cap0/0 | 1.415% no cap89/90 | 14.497% no cap33/35 | 5.260% no cap0/0 | 6.6814% no cap15/18 | 1.220% no cap19/19 | 0.560% no cap26/26 | 4.110% no cap42/42 | 5.705% no cap27/28 |
Composite 複合商品 cap ¥10+0.24 w/w | 3.8826% 61% hd216/291 | 3.516% 65% hd446/465 | 2.4110% 76% hd1,022/1,111 | 2.331% 77% hd671/595 | 2.8519% 71% hd115/134 | 2.3511% 76% hd667/709 | 1.627% 84% hd240/252 | 0.953% 90% hd165/168 | 4.116% 59% hd570/556 | 2.679% 73% hd457/476 |
Monthly trend · shortfall & cleared price
Since April 2025 · markers at the 2026-03-14 regime change and each cap step (19.51 → 15 → 10 ¥)
- Avg cleared ¥/ΔkW·30min (published)
- Cap ¥
- Settled at cap ¥
- Shortfall %
ΔkW price caps (上限価格)
Applicable caps, effective dates and scheduled step-downs
| Product | Current cap | Trajectory (¥/ΔkW·30 min) |
|---|---|---|
| Primary (online) 一次調整力 | ¥10 | ¥19.51 2024-04-01→2026-03-13¥15 2026-03-14→2026-08-31¥10 2026-09-01→ |
| Primary offline 一次オフライン | ¥10 | ¥19.51 2024-04-01→2026-03-13¥15 2026-03-14→2026-08-31¥10 2026-09-01→ · Applies the 一次調整力 cap |
| Secondary ① 二次調整力① | ¥10 | ¥19.51 2024-04-01→2026-03-13¥15 2026-03-14→2026-08-31¥10 2026-09-01→ |
| Secondary ② 二次調整力② | ¥7.21 | ¥7.21 2024-04-01→ |
| Tertiary ① 三次調整力① | ¥7.21 | ¥7.21 2024-04-01→ |
| Tertiary ② 三次調整力② | no cap | No ΔkW cap |
| Composite 複合商品 | ¥10 | ¥19.51 2024-04-01→2026-03-13¥15 2026-03-14→2026-08-31¥10 2026-09-01→ |
Battery share of awarded ΔkW · product × month · new regime
蓄電池 share of awarded MW, nationwide, 2026-03-14 → 2026-11-16 · preliminary (速報値) · resource-type files start 2025-10-01
| Product | 2026-03 | 2026-04 | 2026-05 | 2026-06 | 2026-07 | 2026-08 | 2026-09 | 2026-10 | 2026-11 |
|---|---|---|---|---|---|---|---|---|---|
Primary (online) 一次調整力 | 20% | 22% | 28% | 24% | 23% | 24% | 28% | 35% | 33% |
Primary offline 一次オフライン | 98% | 98% | 99% | 99% | 100% | 100% | 100% | 100% | 100% |
Secondary ① 二次調整力① | 2% | 1% | 2% | 2% | 1% | 2% | 2% | 3% | 2% |
Secondary ② 二次調整力② | 1% | 1% | 1% | 1% | 1% | 1% | 1% | 1% | 1% |
Tertiary ① 三次調整力① | 1% | 1% | 1% | 1% | 1% | 1% | 1% | 1% | 1% |
Tertiary ② 三次調整力② | 0% | 0% | 1% | 0% | 0% | 0% | 1% | 1% | 2% |
Composite 複合商品 | 6% | 6% | 9% | 8% | 9% | 9% | 11% | 13% | 11% |
Monthly resource mix & cleared price by type
Stacked shares of awarded MW (thermal / hydro & pumped / battery / VPP) · battery vs thermal average cleared price
- Battery %
- Battery avg ¥/ΔkW·30min
- Hydro & pumped %
- Thermal %
- Thermal avg ¥/ΔkW·30min
- VPP (aggregated DER) %
Primary (online) · 2026-03-14 → 2026-11-16
248 days in the selected range · nationwide
Resource mix by product · 2026-03-14 → 2026-11-16 (248 days)
Share of awarded MW by type · awarded-MW-weighted average cleared price · battery premium = battery − thermal average price
| Product | Awarded MW/block | Thermal % | Hydro & pumped % | Battery % | VPP (aggregated DER) % | Battery ¥ | Thermal ¥ | Battery premium | Battery bids won/block | Days |
|---|---|---|---|---|---|---|---|---|---|---|
| Primary (online) 一次調整力 | 1,207 | 65.0% | 8.3% | 26.4% | 0.4% | 6.91 | 2.79 | +4.12 | 115.5 | 248 |
| Primary offline 一次オフライン | 212 | 0.0% | 0.0% | 99.6% | 0.4% | 7.95 | — | — | 109.7 | 248 |
| Secondary ① 二次調整力① | 1,139 | 87.1% | 11.1% | 1.9% | 0.0% | 7.51 | 2.62 | +4.89 | 1.2 | 248 |
| Secondary ② 二次調整力② | 2,170 | 79.5% | 19.7% | 0.8% | 0.0% | 7.13 | 2.57 | +4.56 | 2.3 | 248 |
| Tertiary ① 三次調整力① | 3,055 | 82.6% | 16.7% | 0.6% | 0.0% | 7.00 | 2.47 | +4.53 | 2.7 | 248 |
| Tertiary ② 三次調整力② | 483 | 62.6% | 36.6% | 0.4% | 0.4% | 54.40 | 3.31 | +51.09 | 0.6 | 248 |
| Composite 複合商品 | 3,541 | 75.8% | 15.0% | 9.1% | 0.1% | 6.90 | 2.49 | +4.41 | 116.6 | 248 |
Award odds by bid price · Primary (online) (一次調整力) · Tokyo (東京)
2026-10-18 → 2026-11-16 · 30 delivery days, 1,440 half-hours · 30 days are preliminary results · a small bidder paid its own bid
- Accepted
- Revenue per kW-year
- Average accepted
- Best bid of the half-hour
- Ceiling
- Not filled
| Month | Cap | Asked for MW | Bid MW | Bid ÷ asked | Not filled | Average accepted | Ceiling | Best single bid | accepted | ¥ per kW-year |
|---|---|---|---|---|---|---|---|---|---|---|
| 2026-03 · 18 d | ¥15.00 | 481 | 259 | 0.54× | 96.2% | ¥3.98 | ¥14.97 | ¥15.0 | 100% | ¥261,888 |
| 2026-04 | ¥15.00 | 626 | 274 | 0.44× | 100.0% | ¥4.56 | ¥15.00 | ¥15.0 | 100% | ¥262,800 |
| 2026-05 | ¥15.00 | 604 | 273 | 0.45× | 99.2% | ¥4.59 | ¥15.00 | ¥15.0 | 100% | ¥262,800 |
| 2026-06 | ¥15.00 | 462 | 388 | 0.84× | 74.4% | ¥3.91 | ¥14.60 | ¥14.9 | 95% | ¥247,270 |
| 2026-07 | ¥15.00 | 512 | 491 | 0.96× | 54.3% | ¥4.73 | ¥14.23 | ¥14.3 | 88% | ¥221,239 |
| 2026-08 | ¥15.00 | 569 | 531 | 0.93× | 62.0% | ¥4.09 | ¥14.27 | ¥13.9 | 90% | ¥219,797 |
| 2026-09 | ¥10.00 | 499 | 470 | 0.94× | 66.0% | ¥3.93 | ¥9.86 | ¥9.0 | 100% | ¥157,242 |
| 2026-10 | ¥10.00 | 258 | 431 | 1.67× | 14.4% | ¥3.14 | ¥6.85 | ¥5.2 | 77% | ¥70,348 |
| 2026-11 · 16 d | ¥10.00 | 283 | 461 | 1.63× | 10.0% | ¥2.19 | ¥6.50 | ¥6.2 | 72% | ¥77,791 |
- · Small bidder: a bid large enough to push out other accepted bids lowers the ceiling. EPRX publishes the lowest, average and highest accepted price, not the bid list, so that effect cannot be measured.
- · Where composite (複合) awards are counted against a product, its highest accepted price can come from a composite bid. How EPRX counts them is not confirmed.
- · Activation (kWh) payments, assessment penalties and prequalification are outside this table.
- · Past results. Prices fell through 2026 as more capacity bid; the next auction can differ.
Day view · Primary (online) · Tokyo (東京)
48 half-hours of requested vs awarded ΔkW (TSO basis) and cleared prices · 3-hour blocks are expanded for old-regime days
- Avg price ¥ (published)
- Awarded (MW)
- Max award price (as published) ¥
- Requested ΔkW (MW)
- Settled at cap ¥
Japan's balancing market (EPRX): key questions
What is Japan's balancing market (需給調整市場)?
The market run by EPRX (Electric Power Reserve eXchange, 電力需給調整力取引所) in which the transmission and distribution companies of the nine interconnected areas buy balancing capacity (ΔkW) to keep supply and demand matched, in products from primary (一次) to tertiary (三次) reserve. Since trading on 13 March 2026 (delivery from 14 March), every product is bought the day before delivery in 30-minute slots.
What does the shortfall rate mean?
The share of the ΔkW volume a transmission and distribution company requested that was not awarded in the auction. A high shortfall means too few resources offered that product in that area, so the company has to cover the gap by other means.
What is a ΔkW price?
The price paid for holding capacity in reserve, in yen per ΔkW per 30-minute slot (¥/ΔkW·30min). It is separate from the kWh price paid when the reserve is actually used, and it is subject to price caps, shown in the ΔkW price caps panel on this page. To estimate battery revenues, use the BESS and PPA revenue calculator.